AI-generated · Apr 10, 2026Remove the existing Berchtold boom and two light suspensions in Building 500, Room 4416, which are past their lifecycle, and replace them with a Stryker boom (purchased under a separate contract). A Design/Build contractor must hire an Architect/Engineer to produce design intent drawings and a complete set of construction documents with specifications to renovate, remove the old equipment, and install the new boom. A new electrical panel will be installed in the basement to feed the 4th floor, since the current panel cannot carry the additional load. The contractor and the A/E will provide all labor, materials, and technical expertise.
Award has been made to D SQUARE CONSTRUCTION LLC to perform this work, in coordination with the architect/engineer and the separate Stryker boom procurement.
The requirement is to remove existing Berchtold boom and two light suspensions that are past the lifecycle in Building 500 Room 4416. The Design/Build Contractor will engage an Architect/Engineer(A/E) to provide the design intent drawings, a complete set of construction documents with specification reflecting what is required in order to renovate, remove the existing boom and lights and replace with a Stryker boom (purchased on a separate contract). A new electrical panel will be required in the basement to then route up to the 4th floor, as the one presently installed is unable to carry the additional load required. Contractor and A/E are to provide all labor, material and technical expertise to do the work.
From Award Notice posted on Apr 09, 2026Notice history
1-
Award Notice LATEST Posted Apr 09, 2026
Details
Award Information
Award Notices
Posted: Apr 09, 2026
The requirement is to remove existing Berchtold boom and two light suspensions that are past the lifecycle in Building 500 Room 4416. The Design/Build Contractor will engage an Architect/Engineer(A/E) to provide the design intent drawings, a complete set of construction documents with specification...
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| D SQUARE CONSTRUCTION LLC | K514LY25RBX5 | 55WN1 | Tucson, AZ |
Agency
Place of Performance
USA