STONE DS FQ1 FY26 Dockside Repairs 70Z08525RLREP0015
Summary
AI-generated · Aug 24, 2025Dockside repairs to USCGC STONE (WMSL-758), a 418-foot National Security Cutter, require the contractor to provide all labor, services, supplies, materials, equipment power, and personnel necessary to complete 18 defined work items. Tasks include dual point davit maintenance and modification, Oily Water Separator inspection/grooming, incinerator inspection and testing, fuel tank repairs, cleaning and inspecting MP Fuel Service tanks, deck covering repairs and renewals, helicopter hangar door inspection/test and repair, GT Uptake Space inspection/repair/preserve, relocation of the flight deck floodlight transformer, small boat receptacle replacement, weld repairs, wastewater drain piping renewal, shower room deck covering renewal, toilet stud renewal, and fire prevention work, all performed per the solicitation, schedule, and specifications for this cutter.
Amendment history notes changes to the pricing package and specification clarity: Amendment 00001 removed an extra item from the pricing schedule to align with the specification, and the correct Rev1 pricing file is required for bid submission. Amendment 00002 corrected formatting on pricing attachments and addressed questions about the specification (including references to items that were descoped and missing paragraphs), keeping the same 18 work items. Amendment 00003 updated the bid response due time to 10:00 am Eastern Time on a Friday.
This requirement is for the Contractor to provide all necessary labor, services, supplies, materials, equipment power, accessories, personnel, and other things as necessary, except otherwise specified to perform dockside repairs to the USCGC STONE (WMSL-758), a 418-foot National Security Cutter in accordance with the solicitation, schedule, and specifications. Work includes, but is not limited to the following: WORK ITEM 1: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 2: Dual Point Davit, Modify WORK ITEM 3: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 4: Incinerator, Inspect and Test WORK ITEM 5: Fuel Tank, Repairs WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 7: Deck Covering (Polymeric), Repair and Seal WORK ITEM 8: Deck Covering (Polymeric), Renew WORK ITEM 9: Helo Hangar Door, Inspect and Test WORK ITEM 10: Helo Hangar Doors, Repair WORK ITEM 11: GT Uptake Space 01-49-0-Q, Inspect Repair and Preserve WORK ITEM 12: Flight Deck Floodlight Transformer, Motor Driven-Auto, Relocate WORK ITEM 13: Small Boat Receptacles, Replace WORK ITEM 14: Welds (Fan Plenum 02-52-2-Q), Repair WORK ITEM 15: Wastewater Drain Piping, Renew WORK ITEM 16: Deck Covering (Polymeric) Shower Room, Renew WORK ITEM 17: Toilet Stud, Renew WORK ITEM 18: Fire Prevention, Provide
From Solicitation posted on Jun 30, 2025AMENDMENT 00001: is issued to correct Attachment B - Pricing Schedule. The original version of the spreadsheet contained an additional Work Item that was not on the Specification File. Pricing Schedule - STONE (WMSL 418) DS FQ1 FY26_Rev1 1 is the correct version for submission of pricing for this requirement. This requirement is for the Contractor to provide all necessary labor, services, supplies, materials, equipment power, accessories, personnel, and other things as necessary, except otherwise specified to perform dockside repairs to the USCGC STONE (WMSL-758), a 418-foot National Security Cutter in accordance with the solicitation, schedule, and specifications. Work includes, but is not limited to the following: WORK ITEM 1: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 2: Dual Point Davit, Modify WORK ITEM 3: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 4: Incinerator, Inspect and Test WORK ITEM 5: Fuel Tank, Repairs WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 7: Deck Covering (Polymeric), Repair and Seal WORK ITEM 8: Deck Covering (Polymeric), Renew WORK ITEM 9: Helo Hangar Door, Inspect and Test WORK ITEM 10: Helo Hangar Doors, Repair WORK ITEM 11: GT Uptake Space 01-49-0-Q, Inspect Repair and Preserve WORK ITEM 12: Flight Deck Floodlight Transformer, Motor Driven-Auto, Relocate WORK ITEM 13: Small Boat Receptacles, Replace WORK ITEM 14: Welds (Fan Plenum 02-52-2-Q), Repair WORK ITEM 15: Wastewater Drain Piping, Renew WORK ITEM 16: Deck Covering (Polymeric) Shower Room, Renew WORK ITEM 17: Toilet Stud, Renew WORK ITEM 18: Fire Prevention, Provide
From Solicitation posted on Jul 07, 2025AMENDMENT 00002: is issued to correct Attachment B - Pricing Schedule (correct a format error) and Attachment A - Specification file. The update to the Specification file answers the following question: Question: Para 3.1.12 references a work item not included in the specification or provided pricing schedule. Paragraph 3.10.2 references newly installed insulation that is not specified anywhere in the work item. Finally, all paragraphs between 3.1.8 and 3.1.11 are missing. An item was descoped from the dockside plan and it was removed from the specification, which removed the missing paragraphs. Paragraph 3.10.2 addressed by changing verbiage to paint installed vs. newly installed wiring. AMENDMENT 00001: is issued to correct Attachment B - Pricing Schedule. The original version of the spreadsheet contained an additional Work Item that was not on the Specification File. Pricing Schedule - STONE (WMSL 418) DS FQ1 FY26_Rev1 1 is the correct version for submission of pricing for this requirement. This requirement is for the Contractor to provide all necessary labor, services, supplies, materials, equipment power, accessories, personnel, and other things as necessary, except otherwise specified to perform dockside repairs to the USCGC STONE (WMSL-758), a 418-foot National Security Cutter in accordance with the solicitation, schedule, and specifications. Work includes, but is not limited to the following: WORK ITEM 1: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 2: Dual Point Davit, Modify WORK ITEM 3: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 4: Incinerator, Inspect and Test WORK ITEM 5: Fuel Tank, Repairs WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 7: Deck Covering (Polymeric), Repair and Seal WORK ITEM 8: Deck Covering (Polymeric), Renew WORK ITEM 9: Helo Hangar Door, Inspect and Test WORK ITEM 10: Helo Hangar Doors, Repair WORK ITEM 11: GT Uptake Space 01-49-0-Q, Inspect Repair and Preserve WORK ITEM 12: Flight Deck Floodlight Transformer, Motor Driven-Auto, Relocate WORK ITEM 13: Small Boat Receptacles, Replace WORK ITEM 14: Welds (Fan Plenum 02-52-2-Q), Repair WORK ITEM 15: Wastewater Drain Piping, Renew WORK ITEM 16: Deck Covering (Polymeric) Shower Room, Renew WORK ITEM 17: Toilet Stud, Renew WORK ITEM 18: Fire Prevention, Provide
From Solicitation posted on Jul 15, 2025AMENDMENT 00003: is issued to change the Responses Due Time to 10:00 am Eastern Time on Friday 07/25/2025. This amendment moves up the time from the original time of 2:28 pm Eastern Time. AMENDMENT 00002: is issued to correct Attachment B - Pricing Schedule (correct a format error) and Attachment A - Specification file. The update to the Specification file answers the following question: Question: Para 3.1.12 references a work item not included in the specification or provided pricing schedule. Paragraph 3.10.2 references newly installed insulation that is not specified anywhere in the work item. Finally, all paragraphs between 3.1.8 and 3.1.11 are missing. An item was descoped from the dockside plan and it was removed from the specification, which removed the missing paragraphs. Paragraph 3.10.2 addressed by changing verbiage to paint installed vs. newly installed wiring. AMENDMENT 00001: is issued to correct Attachment B - Pricing Schedule. The original version of the spreadsheet contained an additional Work Item that was not on the Specification File. Pricing Schedule - STONE (WMSL 418) DS FQ1 FY26_Rev1 1 is the correct version for submission of pricing for this requirement. This requirement is for the Contractor to provide all necessary labor, services, supplies, materials, equipment power, accessories, personnel, and other things as necessary, except otherwise specified to perform dockside repairs to the USCGC STONE (WMSL-758), a 418-foot National Security Cutter in accordance with the solicitation, schedule, and specifications. Work includes, but is not limited to the following: WORK ITEM 1: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 2: Dual Point Davit, Modify WORK ITEM 3: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 4: Incinerator, Inspect and Test WORK ITEM 5: Fuel Tank, Repairs WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 7: Deck Covering (Polymeric), Repair and Seal WORK ITEM 8: Deck Covering (Polymeric), Renew WORK ITEM 9: Helo Hangar Door, Inspect and Test WORK ITEM 10: Helo Hangar Doors, Repair WORK ITEM 11: GT Uptake Space 01-49-0-Q, Inspect Repair and Preserve WORK ITEM 12: Flight Deck Floodlight Transformer, Motor Driven-Auto, Relocate WORK ITEM 13: Small Boat Receptacles, Replace WORK ITEM 14: Welds (Fan Plenum 02-52-2-Q), Repair WORK ITEM 15: Wastewater Drain Piping, Renew WORK ITEM 16: Deck Covering (Polymeric) Shower Room, Renew WORK ITEM 17: Toilet Stud, Renew WORK ITEM 18: Fire Prevention, Provide
From Solicitation posted on Jul 23, 2025Notice history
4Details
Award Information
Not yet awarded
Contacts
Phone
Phone
Agency
Place of Performance
USA