REPAIR BUTLER DAM W912HN25CA018
Summary
AI-generated · Oct 09, 2025Repairs to Butler Dam require operating the low-level outlet works and performing extensive site work: remove vegetation from the left and right embankments, the auxiliary spillway concrete, and the emergency spillway (including the stone/rock fuse plug); clear the stilling basin and downstream areas in accordance with FEMA guidelines. Reconstruct the stilling basin berm to a uniform shape that can support vehicle traffic to reach the opposite side and accommodate a dedicated outlet structure. Remove downstream stone/rock and debris south of the stilling basin, including accumulated woods.
The project includes validating the scope through topographic survey, geotechnical exploration, and hydrologic and hydraulic studies to define existing conditions and determine upgrades. Prepare design and construction for the channel and storm-water network repair/improvements to properly convey the flow. The award is approximately $4.69 million and goes to WQRI Joint Venture LLC under an 8(a) direct-match procurement.
THIS PROCUREMENT IS AN 8 (A) DIRECT MATCH WITH INTEGRIWARD LLC Repairs to Butler Dam - Project breakdown/Overview as follows: Operate the low-level outlet works. Remove vegetation (trees, brush, plants) from left and right embankments, auxiliary spillway concrete, emergency spillway (including the stone/rock fuse plug), stilling basin and downstream of the basin in accordance with FEMA guidelines. Reconstruct stilling basin berm so that it has a uniform shape, supports vehicle traffic to reach the other side of the dam and has a dedicated outlet structure. Remove stone/rock and debris that was deposited downstream (including the woods) south of the stilling basin. Project requirements shall include validating project scoping requirements such as topographical survey, geotechnical exploration, and hydrologic and hydraulic studies to define existing conditions and determine any upgrade and/or improvement needed to be made. Prepare design and construction for the channel and storm water network repair/improvements to properly convey the flow.
From Award Notice posted on Sep 29, 2025Notice history
1-
Award Notice LATEST Posted Sep 29, 2025
Details
Award Information
Award Notices
Posted: Sep 29, 2025
THIS PROCUREMENT IS AN 8 (A) DIRECT MATCH WITH INTEGRIWARD LLC Repairs to Butler Dam - Project breakdown/Overview as follows: Operate the low-level outlet works. Remove vegetation (trees, brush, plants) from left and right embankments, auxiliary spillway concrete, emergency spillway (including the s...
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| WQRI JOINT VENTURE LLC | KBBFKXTMQXN7 | 86KR7 | Baton Rouge, LA |
Contacts
Phone
Phone
Agency
Place of Performance
USA