Power Installation FA850125Q0058
Summary
AI-generated · Aug 24, 2025Install a 30 KVA transformer and a new 42-circuit, 120/208V, 100-amp electrical panel at the project site. Subsequent notices broaden the scope to include installing a suspended 30 KVA transformer or transformer-panel combo, replacing an existing 208/120V 3-phase electrical panel, and re-routing existing circuits at the same location. A site visit is scheduled, and attachments contain additional details.
Changes between notices: the initial requirement calls for a fixed transformer and a dedicated panel, while later notices allow a suspended transformer or transformer-panel combo and add circuit re-routing, with attendance at the site visit strongly encouraged to gain a complete understanding of the requirement.
The Air Force has a requirement for the installation of one 30 KVA transformer and a new 42 circuit 120/208v 100- amp panel. A site visit has been scheduled for Friday, 18 July. Please refer to the attachments for additional details
From Combined Synopsis/Solicitation posted on Jul 15, 2025The Air Force has a requirement for the installation of a suspended 30 KVA transformer or transformer panel combo, replacement of an existing 208/120V 3-phase electrical panel, and re-routing of existing circuits at the specified project location. Please refer to the attachments for additional details. A site visit has been scheduled for Wednesday, 13 August. It is strongly encouraged that interested vendors attend the site visit to gain a complete understanding of the requirement.
From Combined Synopsis/Solicitation posted on Aug 05, 2025The Air Force has a requirement for the installation of a suspended 30 KVA transformer or transformer panel combo, replacement of an existing 208/120V 3-phase electrical panel, and re-routing of existing circuits at the specified project location. Please refer to the attachments for additional details. A site visit has been scheduled for Wednesday, 13 August. It is strongly encouraged that interested vendors attend the site visit to gain a complete understanding of the requirement.
From Combined Synopsis/Solicitation posted on Aug 11, 2025Notice history
3-
Combined Synopsis/Solicitation Posted Jul 15, 2025
-
Combined Synopsis/Solicitation Posted Aug 05, 2025View changes (2)
- Description: Description was updated
- Response Deadline: Jul 29, 2025 → Aug 19, 2025
-
Combined Synopsis/Solicitation LATEST Posted Aug 11, 2025No changes from previous notice
Details
Award Information
Not yet awarded
Contacts
Agency
Place of Performance
USA