NV FTBL 1094(1) Wilson Campground Road 6982AF25B000025
Summary
AI-generated · Sep 28, 2025Contract would perform improvements to Wilson Campground Road, a 7.23-mile aggregate-surfaced road in the BLM Wilson Reservoir Recreation Management Area, to improve safety, support greater visitor use, and enhance the driving experience. Work includes resurfacing, sight-distance improvements with an alignment shift in an existing S-curve, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements.
The project is split into Schedule A (about 6.21 miles toward campground facilities with hydraulic improvements and S-curve work) and Option X (about 1.01 miles with minor bridge work and hydraulic improvements). Principal tasks include clearing and grubbing (14.4 acres), subexcavation (600 cubic yards), aggregate surface course (22,200 tons), roadbed reconditioning (6.94 miles), minor bridge work, 24-inch equivalent diameter culverts (approximately 520 linear feet), placing conserved topsoil (4,500 cubic yards), and temporary traffic control. The estimated value is $5–$10 million. Plans and specifications are not available, and competition is restricted to small businesses.
THIS IS NOT AN INVITATION FOR BID, PLANS AND SPECIFICATIONS ARE NOT AVAILABLE COMPETITION: TOTAL SMALL BUSINESS SET-ASIDE PROJECT NUMBER: NV FTBL 1094(1) PROJECT NAME: WILSON CAMPGROUND ROAD PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on thenorth end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: Wilson Campground Road project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements. PRINCIPAL WORK ITEMS: 20101-0000 Clearing and Grubbing: 14.4 ACRE 20402-0000 Subexcavation: 600 CUYD 30110-0000 Aggregate Surface Course: 22,200 TON 30301-4000 Roadbed Reconditioning: 6.940 MILE 57501-0000 Minor Bridge Work: LPSM 60202-0400 24-INCH Equivalent Diameter Arch or Elliptical Pipe Culvert: 520 LNFT 62407-0000 Placing Conserved Topsoil: 4,500 CUYD 63501-0000 Temporary Traffic Control: LPSM ANTICIPATED SCHEDULE: Advertisement October 2025 Award December 2025 NTP December 2025 Contract Completion November 2026 DISCLOURE OF MAGNITUDE: Between $5,000,000 and $10,000,000.
From Presolicitation posted on Sep 24, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Oct 20, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Oct 29, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Nov 12, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Nov 19, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Nov 21, 2025NV FTBL 1094(1) Wilson Campground Road PROJECT DESCRIPTION: The Wilson Campground Road Project is located along Wilson Campground Road, 83 miles northwest of Elko, Nevada. The road is located completely within theBureau of Land Management (BLM) Wilson Reservoir Recreation Management Area and is primarily used to access the Wilson Campground Recreation Area on the north end of the project. The need for the project is to improve safety, increase visitor usage, and enhance the driving experience. SCOPE OF THE WORK: The project is comprised of a 7.23-mile aggregate surfaced road along Wilson Campground Road. The proposed improvements as part of this project include resurfacing the existing roads, site distance improvements including an alignment shift along an existing S-curve area, cattle guard adjustments, drainage improvements, minor bridge repairs, and signing replacements. Based on available funding and construction cost analyzed during the scoping phase, the project has been broken into a schedule (Schedule A) and an option(Option X). Schedule A consists of resurfacing the 6.21 miles of aggregate road leading towards the campground facilities, multiple hydraulic improvements, and the S curve area improvements. Option X consists of resurfacing the 1.01 miles of aggregate road leading towards the campground facilities, minor bridge repairs, and multiple hydraulic improvements.
From Solicitation posted on Nov 25, 2025Notice history
7-
Presolicitation Posted Sep 24, 2025
-
Solicitation Posted Oct 20, 2025View changes (3)
- Description: Description was updated
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Not set → Nov 20, 2025
-
Solicitation Posted Oct 29, 2025No changes from previous notice
-
Solicitation Posted Nov 12, 2025No changes from previous notice
-
Solicitation Posted Nov 21, 2025No changes from previous notice
-
Solicitation LATEST Posted Nov 25, 2025No changes from previous notice