AI-generated · Aug 24, 2025Replace the HVAC system for Building 1585 at Yokota Air Base, including the building chiller and pumps, five Central Station Air Handling Units with associated Variable Air Volume boxes, installation of a new hydronic reheat system, and implementation of new DDC controls. Modernize the sterile processing department by moving it from the second to the first floor and creating a new three-room standard template for decontamination, sterile assembly, and sterile storage; the existing sterilization space will be repurposed for a different use.
Access all project documents through the PIEE website; amendments have updated specifications, drawings, and RFIs, and include revised site visit details.
25 July 25: Amendment 0002 posted. Revised specifications, drawings, and answered RFIs. Please read amendment for details. 14 May 25: Amendment 0001 posted Site Visit Date has changed to 27 May 25. Please read amendment for details. This project will replace the HVAC system including the building chiller and associated pumps, 5 Central Station Air Handling Units and associated Variable Air Volume Boxes, installation of a new hydronic reheat system, and implementation of new DDC Controls along with modernizing the sterile processing department for building 1585. A new layout for the sterilization department will provide a three-room standard template for decontamination, sterile assembly and sterile storage. The sterilization department will move from the second floor to the first floor. The existing sterilization department will be converted to a different use. Please download all files in PIEE Website.
From Solicitation posted on Jul 25, 202528 August 25: Bid opened and OF 1419 Bid Abstract posted. 31 July 25: Extended bid due date to 28 Aug 25. 25 July 25: Revised specifications, drawings, and answered RFIs. 14 May 25: Site Visit Date has changed to 27 May 25. Please read amendment for details. This project will replace the HVAC system including the building chiller and associated pumps, 5 Central Station Air Handling Units and associated Variable Air Volume Boxes, installation of a new hydronic reheat system, and implementation of new DDC Controls along with modernizing the sterile processing department for building 1585. A new layout for the sterilization department will provide a three-room standard template for decontamination, sterile assembly and sterile storage. The sterilization department will move from the second floor to the first floor. The existing sterilization department will be converted to a different use. Please download all files in PIEE Website.
From Solicitation posted on Aug 28, 2025Notice history
2-
-
Solicitation LATEST Posted Aug 28, 2025View changes (2)
- Description: Description was updated
- Response Deadline: Aug 22, 2025 → Aug 28, 2025
Details
Award Information
Not yet awarded
Contacts
Agency
Place of Performance
YOKOTA AB