Award Notice 5 notices

Eglin AFB Paving IDIQ FA282325R0023

Solicitation FA282325R0023 Copied Notice ID 51b567cb8e0a41be838e81c65a85ef07 Copied DEPT OF DEFENSE — FA2823 AFTC PZIO
SAM.gov
Posted
Feb 25, 2026
Deadline
No deadline
Set-aside
None
NAICS
N/A
PSC
N/A

Summary

AI-generated · Aug 24, 2025

Provide asphalt paving and concrete support for Eglin AFB, including resurfacing, full-depth reconstruction, and new full-depth construction of bituminous concrete and Portland cement concrete pavements. Work is to be self-performed (not subcontracted to others) and includes clearing, excavating, and grading related to the construction of airfield pavements, roads, streets, railroads, and culverts.

Contractor must have in-house asphalt testing capabilities and in-house asphalt production within a reasonable distance to deliver temperature-sensitive asphalt for large airfield and roadway projects. The ability to place at least 1,500 tons of airfield pavement per day during runway milling and overlay is required, along with tasks such as curb return widenings, new construction of bituminous concrete ramp-downs, crack repair on bituminous pavement, and construction of concrete foundation walls and footings.

This project includes, but is not limited to, providing asphalt paving and concrete support to Eglin AFB, FL. This requirement consists of resurfacing, full depth reconstruction, and new full-deep construction of bituminous concrete and portland cement concrete pavements. This work shall be self-performing and not sub-contracted out to a third party. Contractors shall have in-house laboratory capabilities of testing asphalt. Contractors in-house asphalt production shall be within reasonable distance to deliver temperature sensitive asphalt for large road construction and airfield construction projects. Clearing, excavating, grading and associated operations related to the construction of airfield pavements, roads, streets, railroads and culverts complete. Contractor shall be capable of placing at least 1,500 Tons of Airfield Pavement per day during runway milling and overlay construction. Construction of curb return widenings, new construction of bituminous concrete ramp-downs, crack repair in bituminous concrete pavement, new construction of concrete foundation walls and footings. Questions Due By: 9 September 2025 2:00 P.M. CDT

From Solicitation posted on Aug 21, 2025

This project includes, but is not limited to, providing asphalt paving and concrete support to Eglin AFB, FL. This requirement consists of resurfacing, full depth reconstruction, and new full-deep construction of bituminous concrete and portland cement concrete pavements. This work shall be self-performing and not sub-contracted out to a third party. Contractors shall have in-house laboratory capabilities of testing asphalt. Contractors in-house asphalt production shall be within reasonable distance to deliver temperature sensitive asphalt for large road construction and airfield construction projects. Clearing, excavating, grading and associated operations related to the construction of airfield pavements, roads, streets, railroads and culverts complete. Contractor shall be capable of placing at least 1,500 Tons of Airfield Pavement per day during runway milling and overlay construction. Construction of curb return widenings, new construction of bituminous concrete ramp-downs, crack repair in bituminous concrete pavement, new construction of concrete foundation walls and footings. Questions Due By: 9 September 2025 2:00 P.M. CDT

From Solicitation posted on Sep 16, 2025

This project includes, but is not limited to, providing asphalt paving and concrete support to Eglin AFB, FL. This requirement consists of resurfacing, full depth reconstruction, and new full-deep construction of bituminous concrete and portland cement concrete pavements. This work shall be self-performing and not sub-contracted out to a third party. Contractors shall have in-house laboratory capabilities of testing asphalt. Contractors in-house asphalt production shall be within reasonable distance to deliver temperature sensitive asphalt for large road construction and airfield construction projects. Clearing, excavating, grading and associated operations related to the construction of airfield pavements, roads, streets, railroads and culverts complete. Contractor shall be capable of placing at least 1,500 Tons of Airfield Pavement per day during runway milling and overlay construction. Construction of curb return widenings, new construction of bituminous concrete ramp-downs, crack repair in bituminous concrete pavement, new construction of concrete foundation walls and footings. Questions Due By: 9 September 2025 2:00 P.M. CDT

From Solicitation posted on Sep 17, 2025

This project includes, but is not limited to, providing asphalt paving and concrete support to Eglin AFB, FL. This requirement consists of resurfacing, full depth reconstruction, and new full-deep construction of bituminous concrete and portland cement concrete pavements. This work shall be self-performing and not sub-contracted out to a third party. Contractors shall have in-house laboratory capabilities of testing asphalt. Contractors in-house asphalt production shall be within reasonable distance to deliver temperature sensitive asphalt for large road construction and airfield construction projects. Clearing, excavating, grading and associated operations related to the construction of airfield pavements, roads, streets, railroads and culverts complete. Contractor shall be capable of placing at least 1,500 Tons of Airfield Pavement per day during runway milling and overlay construction. Construction of curb return widenings, new construction of bituminous concrete ramp-downs, crack repair in bituminous concrete pavement, new construction of concrete foundation walls and footings. Questions Due By: 9 September 2025 2:00 P.M. CDT

From Solicitation posted on Sep 18, 2025

Purpose of this edit is to update total award value from $20,000,000,000.00 to $200,000,000.00

From Award Notice posted on Feb 25, 2026

Notice history

5
  1. Solicitation Posted Aug 21, 2025 View
  2. Solicitation Posted Sep 16, 2025
    No changes from previous notice
  3. Solicitation Posted Sep 17, 2025
    • Response Deadline: Sep 22, 2025Sep 24, 2025
  4. Solicitation Posted Sep 18, 2025
    No changes from previous notice
  5. Award Notice LATEST Posted Feb 25, 2026

Details

Solicitation number FA282325R0023
Notice ID 51b567cb8e0a41be838e81c65a85ef07
Award number FA282326D0004
Notice type Award Notice
Archive date Mar 10, 2026

Award Information

Awardee
1
Total Awarded
$200,000,000.00
Award Date
Feb 23, 2026

Award Notices

Eglin AFB Paving IDIQ View Notice

Posted: Feb 25, 2026

Purpose of this edit is to update total award value from $20,000,000,000.00 to $200,000,000.00

Awardees

Company Name UEI CAGE Code Location
C.W. ROBERTS CONTRACTING, INCORPORATED MEMUPG8MKRW8 0CHA7 Tallahassee, FL

Documents

No files available

View on SAM.gov

Contacts

primary
Jason Ward

Email

Phone

Agency

DEPT OF DEFENSE
DEPT OF THE AIR FORCE
AIR FORCE MATERIEL COMMAND
AIR FORCE TEST CENTER
FA2823 AFTC PZIO

Place of Performance

Dates

Posted Feb 25, 2026 5 months ago
Last Updated Aug 06, 2026 2 days ago