Cedar Rapids Flood Risk Management Project, Reach 4 Phase 1 Downstream River Floodwall and Pump Station W912EK26CA016
Summary
AI-generated · May 05, 2026Contract awarded for the Cedar Rapids Flood Risk Management Project, Reach 4 Phase 1 Downstream River Floodwall and Pump Station to the low bidder General Constructors Inc. of the Quad Cities under solicitation W912EK26BA001 for $40,391,096. The scope covers constructing the downstream floodwall and pump station as part of Reach 4 Phase 1 to improve flood risk management in Cedar Rapids.
Award made to the low bidder and per soliciation W912EK26BA001
From Award Notice posted on May 04, 2026Notice history
1-
Award Notice LATEST Posted May 04, 2026
Details
Award Information
Award Notices
Posted: May 04, 2026
Award made to the low bidder and per soliciation W912EK26BA001
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| GENERAL CONSTRUCTORS INC. OF THE QUAD CITIES | C9JGVNMG4ND3 | 00XT6 | Bettendorf, IA |
Contacts
Agency
Place of Performance
USA