Y1DA--614-20-109 Cooling Tower Replacement 36C24925B0010
Summary
AI-generated · Aug 23, 2025Replace the main cooling tower at the Memphis VA Medical Center, along with condenser water pumps and primary/secondary chilled water pumps, and provide all necessary tools, labor, materials, permits, licenses, supervision, and quality control. A temporary portable cooling tower will be used to maintain capacity during equipment ordering and installation, and the work must be completed within 365 calendar days from the Notice to Proceed. This is a 100% SDVOSB set-aside; the awardee must be listed in the DSBS and have an active SAM registration, enroll in VETS4212, and be deemed responsible under FAR Part 9. The design allows equal cooling towers if they meet all requirements, but the original equipment manufacturer BAC is preferred as the basis of design, and new towers must install on the existing concrete basins with base dimensions matching the MP601 schedule; there is no new concrete work, though interior concrete painting may apply where specified, and the hot water distribution basin at the top shall be stainless steel with discharges into the existing basins.
A clarifying Q&A clarifies that Division 03 concrete is not used and there is no concrete work beyond painting existing concrete; the existing concrete cooling tower basins will remain and be reused for the new towers, with no requirement for new basins or duct banks. The government is open to equal towers rather than brand-only solutions, but brand-name BAC is noted as preferred for space constraints and is called out as the basis of design in MP601. Submittal questions are to be addressed in writing to the Contracting Officer, and no awards have been recorded to date.
The Lt. Col. Luke J. Weathers, Jr. VA Medical Center in Memphis, TN 38104 has a requirement for Project# : 614-20-109 Cooling Tower Replacement. This will be a 100% set-aside for Service-Disabled Veteran-Owned Small Business concerns under the authority of 38 U.S.C section 8127 (d). NAICS code 238220- Plumbing, Heating, and Air-Conditioning Contractors applies to this requirement. The small business size standard is $19M. The estimated range of construction is Between $2,000,000.00 and $5,000,000.00. This requirement will be procured per Federal Acquisition Regulation (FAR) Part 14.101 - Sealed Bidding. The solicitation is expected to be posted on or around July 10th, 2025, and close on or around August 15th, 2025. This requirement is a 100% set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns under the authority of 38 U.S.C 8127 (d). Only those SDVOSB s listed and viewable in the dsbs.sba.gov database located https://dsbs.sba.gov/. The dsbs.sba.gov database will be checked at the time of offer submission as well as prior to award. All offers must also have an active listing in the System for Award Management (SAM) database. The awarded contractor must also submit evidence of enrollment with VETS4212. In addition to the requirements as set forth in the solicitation notice (to be issued), the proposed contractor must also be determined responsible in accordance with FAR Part 9. The Contracting Officer will determine responsibility prior to award any award being made. Questions related to this requirement will only be addressed in writing by way of email to the Contracting Officer at Michael.brown1305@va.gov. The Project number, Project Name and Solicitation Number must be included in the subject line of all questions related to this requirement. Note: No questions will be considered until the actual solicitation is released, on or by July 10th, 2025. At that time the solicitation will identify when questions are due to the contracting officer. Statement of Work The contractor shall replace the main cooling tower along with the condenser water pumps and primary and secondary chilled water pumps, provide all necessary tools, labor, materials, equipment, permits, license, supervision, and quality control to the project Cooling Tower Replacement at the Lt. Col. Luke J. Weathers, Jr. VA Medical Center in Memphis TN, in accordance with the drawings and specifications. A temporary portable cooling tower will be used to support the available capacity during the equipment ordering process and installation. Performance Period: The contractor shall complete the work required in a total of 365 calendar days from the date of issuance of the Notice to Proceed.
From Presolicitation posted on Jun 25, 2025614-20-109 Cooling Tower Replacement
From Solicitation posted on Jul 08, 202536C24925B0010 614-20-109 Cooling Tower Replacement The specs document page 23 list concrete as NOT USED . Would the government please confirm contractor is to use/leave existing walls and concrete base? A: For clarity, it is understood the question refers to page 3 (not 23) of 398, Table of Contents, which states, DIVISION 03 CONCRETE NOT USED. Although there is no concrete work, section 099100 Painting applies to painting existing concrete. [Lee to verify Client wants interior concrete painted. Also, are ALL engineering disciplines sure we have no new concrete??? No concrete duct banks??? No equipment pads??? Electrical specs have concrete!!!] Would the government please confirm the contractor is to use the existing basins? A: The existing concrete cooling tower basins shall remain and will be reused for the new cooling towers. The submittals reference stainless steel basins, does that imply new basins? A: The cooling towers have an open bottom and discharges into the existing concrete basins. The hot water distribution basin at the top of the towers shall be constructed of stainless steel. Is the government open to similar Towers or brand name specific? A: The government is open to equal cooling towers. However, the cooling tower must meet all design conditions and specifically, the new cooling tower base dimensions must match the existing cooling tower as specified in the schedule on sheet MP601. New towers must be installed on the existing concrete basins. Would the government specify preferred brand or OEM? A: Due to size constraints in the existing area, the original equipment manufacturer, B.A.C., would be preferred, additionally it has been specifically called out as the basis of design in the Cooling Tower Schedule on sheet MP601.
From Solicitation posted on Jul 23, 2025614-20-109 Cooling Tower Replacement
From Solicitation posted on Aug 13, 2025Notice history
5-
-
Solicitation Posted Jul 08, 2025View changes (4)
- Description: Description was updated
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Not set → Aug 14, 2025
- Set-Aside: Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) → None
-
Solicitation Posted Aug 13, 2025View changes (2)
- Description: Description was updated
- Response Deadline: Aug 14, 2025 → Aug 18, 2025
-
Award Notice LATEST Posted Sep 16, 2025
Details
Award Information
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| BWIS GTG JV LLC | SKGUACNAXQJ2 | 9Y8A8 | NEW YORK |
Contacts
Contract Specialist
Phone