Y--NV-DESERT NWRC-FIRE CACHE AND BUNKHOUSE 140F1B25R0004
Summary
AI-generated · Aug 24, 2025Design-build the Nevada Fire Zone Fire Complex at Desert NWR Corn Creek to consolidate decentralized fire operations into a centralized facility, providing administration, vehicle/equipment storage, personnel readiness, and fire operations planning spaces. The project covers both design and construction of permanent facilities and is expected to be completed in about 465 calendar days from NTP, under a firm-fixed-price contract in the $10–$14 million range. Procurement will use a two-phase design-build approach (Phase I design, Phase II construction), with solicitation documents posted only on SAM.gov and no hard copies.
Changes from the initial notice include a formal 100% small-business set-aside, Davis-Bacon wage determinations, and required bonds (100% performance and payment bonds) to be provided within 10 calendar days after award. Proposals must follow the specified submission formats (e.g., SF1442, pricing forms) and demonstrate Nevada licensing/compliance; the contractor must perform under local, state, and federal construction regulations. A site visit is encouraged, questions must be submitted in writing via email, and final award will be based on the technical approach and price, with SAM registration required to be eligible.
This is a Pre-solicitation Notice issued in accordance with FAR 5.204. The U.S. Fish and Wildlife Service (FWS) intends to issue a solicitation for the design and construction of the Nevada Fire Zone Fire Complex located within the Corn Creek administrative area at Desert NWR, just north of Las Vegas, Nevada. Desert NWR encompasses six major mountain ranges and seven distinct life zones, supporting a rich ecological system across Southern Nevada. The Nevada Fire Zone program serves all the refuges in the Desert NWR Complex and supports wildfire suppression, vegetation control, prescribed burns, and habitat management through coordinated fire operations. The planned Fire Complex will consolidate currently decentralized operations and staff into a single, centralized location to support safe, efficient, and long-term operational effectiveness. The project includes full design and construction of permanent fire facilities to support administration, vehicle/equipment storage, personnel readiness, and fire operations planning. Anticipated Contract Type: Firm-Fixed Price (FFP), Design-Build Construction Contract Estimated Magnitude of Construction: Between $10,000,000 and $14,000,000 (IAW FAR 36.204) Place of Performance: Corn Creek Administrative Area Desert National Wildlife Refuge Las Vegas, Nevada Period of Performance: Approximately 465 calendar days from Notice to Proceed (NTP) Anticipated Solicitation Issue Date: On or about July 31, 2025 Additional Information for Interested Vendors: - This will be a Design-Build acquisition using a two-phase selection process as outlined in FAR Subpart 36.3. - Solicitation documents will be available only on SAM.gov and link with additional supporting document; no hard copies will be provided through direct email. - All responsible sources may submit a proposal for Phase I to advance to Phase II. The solicitation is issued in accordance with all terms and conditions; specification and attachments/exhibits. - Interested vendors should monitor the SAM.gov website for updates, amendments, and the final solicitation. Disclaimer: This notice is issued solely for informational and planning purposes and does not constitute a solicitation or a Request for Proposal (RFP). Responses to this notice are not offers and cannot be accepted by the Government to form a binding contract. The Government will not reimburse any costs incurred in response to this notice.
From Presolicitation posted on Jul 16, 2025Desert National Wildlife Refuge Design/Construct Nevada Fire Zone Fire Complex The U.S. Fish and Wildlife Service (FWS) is seeking qualified contractors to perform both Phase I (Design) and Phase II (Construction) services for the Design-Build of the Nevada Fire Zone Fire Complex. The selected contractor shall furnish all labor, materials, equipment, tools, supervision, and services necessary to complete the full design and construction effort in accordance with the scope of work. The project includes design/build complex for the Desert NWR encompasses six major mountain ranges and seven distinct life zones, supporting a rich ecological system across Southern Nevada. The Nevada Fire Zone program serves all the refuges in the Desert NWR Complex and supports wildfire suppression, vegetation control, prescribed burns, and habitat management through coordinated fire operations. The planned Fire Complex will consolidate currently decentralized operations and staff into a single, centralized location to support safe, efficient, and long-term operational effectiveness. The project includes full design and construction of permanent fire facilities to support administration, vehicle/equipment storage, personnel readiness, and fire operations planning. The compliance and quality assurance shall follow all local, state, and federal regulations governing construction activities. The construction magnitude is estimated between $10,000,000.00 to $14,000,000.00. 100% performance bonds and payment bonds will be required. The office is located: Corn Creek Administrative Area Desert National Wildlife Refuge Las Vegas, Nevada Performance Period and Completion: NTP + 465 Calendar Days Wage Rates: General Wage Rate Decision Number: NV20250038 Construction Type: Building Date: (05/02/2025) State: Nevada County: Clark County This acquisition is subject to the Davis-Bacon Act. Applicable wage determination(s) are provided within the solicitation. Contractors must comply with minimum wage and labor standards set forth therein. This Request for Proposal (RFP) is a TOTAL SMALL BUSINESS SET ASIDE and is conducted under the procedures of FAR Parts 12 and 13, incorporating provisions and clauses in effect through Federal Acquisition Circular 2025-06. The NAICS code is 236220 and the small business size standard is $45.0m. Instructions to offeror: All responsible small business sources shall review all documentation and submit a proposal, which shall be considered by the agency. The contractor shall demonstrate within the proposal relevant experience to successfully complete as followed; all state and local law; provides appropriate licensed and certified within the state of Nevada. Offerors shall submit a technical proposal detailing their approach to construction, including schedule, labor resources, Subcontracting Plan, and compliance with applicable building codes and safety standards. Refer to (Section L) & (Section M) for formats, contents, and page limits. Furthermore, see the statement of work and attachments for additional details to create Volume (I & II) & TABs to address the technical approach(s) and pricing to the standard of Phase (I&II). The Award will be made as a firm-fixed-price contract. The basis of contract will be on technical approach and Price, as acceptability for this requirement below. Award of the contract will be made to a responsible source pursuant to FAR subpart 9.1. Please submit your proposal with solicitation document (showing unit and total price) on company letterhead or Pricing Bid structure/Form; SAM.gov UEI code; point of contact phone number and e- mail address. Refer to FAR provision 52.212-1 Instructions to Offerors Commercial Items for additional submission guidance and include a copy of FAR provision 52.212-3 Offeror Representations and Certifications -- Commercial Items with applicable sections completed. Bonds: All bid bonds are required (Section H). Contractors shall provide evidence of appropriate construction licensing and bonding in accordance with FAR 28.102-1 and FAR 52.228-15, Performance and Payment BondsConstruction. All required bonds must be submitted no later than 10 calendar days after award. Failure to provide required bonds may result in contract termination for default. Site Visit Acknowledgement Offerors are strongly encouraged to attend the scheduled site visit to gain a comprehensive understanding of the project location and site conditions. Information regarding the date, time, and access instructions for the site visit is provided in Section L. Any questions arising from the site visit shall be submitted in writing per the instructions in Section L. Any and all questions shall be submitted via email only; no verbal questions will be accepted. Please be sure to include the solicitation number in your proposal and in the subject line of any email submitted. E-Mail Submission for Questions & Proposals: terrence_anderson@fws.gov Site Visit: 12:00 PM 1:00 PM ED - August 25, 2025, 8: 30A.M 11: 00A.M PCT Question Deadline Date: Phase I - August 4, 2025, 10:00 AM CST Phase II - August 29, 2025, 10:00 AM CST Final Proposal Due: (Phase I & II) - 9:00 AM CST Thursday September 11, 2025 Solicitation Package: SF1442 - Solicitation Pricing Form Clauses & Provisions (Terms and Conditions) Wage Rate Determination Attachment 1 - Statement of Work (SOW) (2-11) Attachments In order to have a quote considered for award, respondent must be registered at the System for Award Management (SAM) website (https://www.sam.gov ) as an active vendor by the time an award decision is necessary.
From Solicitation posted on Jul 29, 2025Desert National Wildlife Refuge Design/Construct Nevada Fire Zone Fire Complex The U.S. Fish and Wildlife Service (FWS) is seeking qualified contractors to perform both Phase I (Design) and Phase II (Construction) services for the Design-Build of the Nevada Fire Zone Fire Complex. The selected contractor shall furnish all labor, materials, equipment, tools, supervision, and services necessary to complete the full design and construction effort in accordance with the scope of work. The project includes design/build complex for the Desert NWR encompasses six major mountain ranges and seven distinct life zones, supporting a rich ecological system across Southern Nevada. The Nevada Fire Zone program serves all the refuges in the Desert NWR Complex and supports wildfire suppression, vegetation control, prescribed burns, and habitat management through coordinated fire operations. The planned Fire Complex will consolidate currently decentralized operations and staff into a single, centralized location to support safe, efficient, and long-term operational effectiveness. The project includes full design and construction of permanent fire facilities to support administration, vehicle/equipment storage, personnel readiness, and fire operations planning. The compliance and quality assurance shall follow all local, state, and federal regulations governing construction activities. The construction magnitude is estimated between $10,000,000.00 to $14,000,000.00. 100% performance bonds and payment bonds will be required. The office is located: Corn Creek Administrative Area Desert National Wildlife Refuge Las Vegas, Nevada Performance Period and Completion: NTP + 465 Calendar Days Wage Rates: General Wage Rate Decision Number: NV20250038 Construction Type: Building Date: (05/02/2025) State: Nevada County: Clark County This acquisition is subject to the Davis-Bacon Act. Applicable wage determination(s) are provided within the solicitation. Contractors must comply with minimum wage and labor standards set forth therein. This Request for Proposal (RFP) is a TOTAL SMALL BUSINESS SET ASIDE and is conducted under the procedures of FAR Parts 12 and 13, incorporating provisions and clauses in effect through Federal Acquisition Circular 2025-06. The NAICS code is 236220 and the small business size standard is $45.0m. Instructions to offeror: All responsible small business sources shall review all documentation and submit a proposal, which shall be considered by the agency. The contractor shall demonstrate within the proposal relevant experience to successfully complete as followed; all state and local law; provides appropriate licensed and certified within the state of Nevada. Offerors shall submit a technical proposal detailing their approach to construction, including schedule, labor resources, Subcontracting Plan, and compliance with applicable building codes and safety standards. Refer to (Section L) & (Section M) for formats, contents, and page limits. Furthermore, see the statement of work and attachments for additional details to create Volume (I & II) & TABs to address the technical approach(s) and pricing to the standard of Phase (I&II). The Award will be made as a firm-fixed-price contract. The basis of contract will be on technical approach and Price, as acceptability for this requirement below. Award of the contract will be made to a responsible source pursuant to FAR subpart 9.1. Please submit your proposal with solicitation document (showing unit and total price) on company letterhead or Pricing Bid structure/Form; SAM.gov UEI code; point of contact phone number and e- mail address. Refer to FAR provision 52.212-1 Instructions to Offerors Commercial Items for additional submission guidance and include a copy of FAR provision 52.212-3 Offeror Representations and Certifications -- Commercial Items with applicable sections completed. Bonds: All bid bonds are required (Section H). Contractors shall provide evidence of appropriate construction licensing and bonding in accordance with FAR 28.102-1 and FAR 52.228-15, Performance and Payment BondsConstruction. All required bonds must be submitted no later than 10 calendar days after award. Failure to provide required bonds may result in contract termination for default. Site Visit Acknowledgement Offerors are strongly encouraged to attend the scheduled site visit to gain a comprehensive understanding of the project location and site conditions. Information regarding the date, time, and access instructions for the site visit is provided in Section L. Any questions arising from the site visit shall be submitted in writing per the instructions in Section L. Any and all questions shall be submitted via email only; no verbal questions will be accepted. Please be sure to include the solicitation number in your proposal and in the subject line of any email submitted. E-Mail Submission for Questions & Proposals: terrence_anderson@fws.gov Site Visit: 12:00 PM 1:00 PM ED - August 25, 2025, 8: 30A.M 11: 00A.M PCT Question Deadline Date: Phase I - August 4, 2025, 10:00 AM CST Phase II - August 29, 2025, 10:00 AM CST Final Proposal Due: (Phase I & II) - 9:00 AM CST Thursday September 11, 2025 Solicitation Package: SF1442 - Solicitation Pricing Form Clauses & Provisions (Terms and Conditions) Wage Rate Determination Attachment 1 - Statement of Work (SOW) (2-11) Attachments In order to have a quote considered for award, respondent must be registered at the System for Award Management (SAM) website (https://www.sam.gov ) as an active vendor by the time an award decision is necessary.
From Solicitation posted on Aug 05, 2025NV-DESERT NWRC-FIRE CACHE AND BUNKHOUSE - Line-Item associated with 1,2,3,6
From Award Notice posted on Sep 23, 2025Notice history
4-
Presolicitation Posted Jul 16, 2025
-
Solicitation Posted Jul 29, 2025View changes (4)
- Title: Y--NV-DESERT NWRC-FIRE CACHE AND BUNKHOUSE → FWS - DESERT NWRC - Design-Build CACHE & BUNKHOUSE
- Description: Description was updated
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Jul 30, 2025 → Sep 11, 2025
-
Solicitation Posted Aug 05, 2025View changes (2)
- Title: FWS - DESERT NWRC - Design-Build CACHE & BUNKHOUSE → Y--FWS - DESERT NWRC - Design-Build CACHE & BUNKHOUSE
- Response Deadline: Sep 11, 2025 → Aug 06, 2025
-
Award Notice LATEST Posted Sep 23, 2025
Details
Award Information
Award Notices
Posted: Sep 23, 2025
NV-DESERT NWRC-FIRE CACHE AND BUNKHOUSE - Line-Item associated with 1,2,3,6
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| DOFINE SPRINKLER REBUILDERS INC | SEMCHAJ79BZ5 | 7HNC5 | Burley, ID |
Contacts
Phone