W912P626BA003 Chesterton Interceptor Rehabilitation W912P626BA003
Summary
AI-generated · Oct 30, 2025Rehabilitation of a 48-inch RCP sewer interceptor along 8th Street in Chesterton, Indiana, using segmented slip lining to extend the pipe’s life. Insertion pits will be used, with pipe segments lowered into the pit and pushed into the sewer using a hydraulic press.
The project runs roughly 3,300 feet, spanning from the intersection of 8th Street and Morgan Avenue to the wastewater treatment plant on League Lane.
The project aims to extend the life of the 48-inch RCP sewer interceptor along 8th Street by using segmented slip lining for the pipe. Insertion pits will be utilized, with segments of the pipes being lowered into the pit and pushed into the sewer using a hydraulic press. The pipe will span from 8th Street & Morgan Avenue to the wastewater treatment plant on League Lane, approximately 3,300 feet in length, in Chesterton, Indiana.
From Presolicitation posted on Oct 29, 2025PROJECT TITLE: CHESTERTON INTERCEPTOR REHABILITATION, CHESTERTON, PORTER COUNTY, INDIANAPROJECT LOCATION: CHESTERTON, PORTER COUNTY, INDIANATHE PROJECT AIMS TO EXTEND THE LIFE OF THE 48-INCH RCP SEWER INTERCEPTOR ALONG 8TH STREET VIA SEGMENTED SLIP LINING THE PIPE. INSERTION PITS WILL BE USED, AND SEGMENTS OF THE PIPES WILL BE LOWERED DOWN INTO THE PIT AND PUSHED INTO THE SEWER VIA A HYDRAULIC PRESS. THE PIPE WILL SPAN FROM 8TH STREET AND MORGAN AVENUE TO THE WASTEWATER TREATMENT PLANT ON LEAGUE LANE APPROXIMATELY 3,300 FEET LONG IN CHESTERTON INDIANA.
From Solicitation posted on Jan 30, 2026PROJECT TITLE: CHESTERTON INTERCEPTOR REHABILITATION, CHESTERTON, PORTER COUNTY, INDIANAPROJECT LOCATION: CHESTERTON, PORTER COUNTY, INDIANATHE PROJECT AIMS TO EXTEND THE LIFE OF THE 48-INCH RCP SEWER INTERCEPTOR ALONG 8TH STREET VIA SEGMENTED SLIP LINING THE PIPE. INSERTION PITS WILL BE USED, AND SEGMENTS OF THE PIPES WILL BE LOWERED DOWN INTO THE PIT AND PUSHED INTO THE SEWER VIA A HYDRAULIC PRESS. THE PIPE WILL SPAN FROM 8TH STREET AND MORGAN AVENUE TO THE WASTEWATER TREATMENT PLANT ON LEAGUE LANE APPROXIMATELY 3,300 FEET LONG IN CHESTERTON INDIANA.
From Solicitation posted on Feb 02, 2026PROJECT TITLE: CHESTERTON INTERCEPTOR REHABILITATION, CHESTERTON, PORTER COUNTY, INDIANAPROJECT LOCATION: CHESTERTON, PORTER COUNTY, INDIANATHE PROJECT AIMS TO EXTEND THE LIFE OF THE 48-INCH RCP SEWER INTERCEPTOR ALONG 8TH STREET VIA SEGMENTED SLIP LINING THE PIPE. INSERTION PITS WILL BE USED, AND SEGMENTS OF THE PIPES WILL BE LOWERED DOWN INTO THE PIT AND PUSHED INTO THE SEWER VIA A HYDRAULIC PRESS. THE PIPE WILL SPAN FROM 8TH STREET AND MORGAN AVENUE TO THE WASTEWATER TREATMENT PLANT ON LEAGUE LANE APPROXIMATELY 3,300 FEET LONG IN CHESTERTON INDIANA. THE PREBID MEETING DETAILS ARE POSTED UNDER THIS UPDATE.
From Solicitation posted on Feb 09, 2026PROJECT TITLE: CHESTERTON INTERCEPTOR REHABILITATION, CHESTERTON, PORTER COUNTY, INDIANAPROJECT LOCATION: CHESTERTON, PORTER COUNTY, INDIANATHE PROJECT AIMS TO EXTEND THE LIFE OF THE 48-INCH RCP SEWER INTERCEPTOR ALONG 8TH STREET VIA SEGMENTED SLIP LINING THE PIPE. INSERTION PITS WILL BE USED, AND SEGMENTS OF THE PIPES WILL BE LOWERED DOWN INTO THE PIT AND PUSHED INTO THE SEWER VIA A HYDRAULIC PRESS. THE PIPE WILL SPAN FROM 8TH STREET AND MORGAN AVENUE TO THE WASTEWATER TREATMENT PLANT ON LEAGUE LANE APPROXIMATELY 3,300 FEET LONG IN CHESTERTON INDIANA. THE PREBID MEETING DETAILS ARE POSTED UNDER THIS UPDATE. AMENDMENT 0002 HAS BEEN POSTED.
From Solicitation posted on Mar 02, 2026PROJECT TITLE: CHESTERTON INTERCEPTOR REHABILITATION, CHESTERTON, PORTER COUNTY, INDIANAPROJECT LOCATION: CHESTERTON, PORTER COUNTY, INDIANATHE PROJECT AIMS TO EXTEND THE LIFE OF THE 48-INCH RCP SEWER INTERCEPTOR ALONG 8TH STREET VIA SEGMENTED SLIP LINING THE PIPE. INSERTION PITS WILL BE USED, AND SEGMENTS OF THE PIPES WILL BE LOWERED DOWN INTO THE PIT AND PUSHED INTO THE SEWER VIA A HYDRAULIC PRESS. THE PIPE WILL SPAN FROM 8TH STREET AND MORGAN AVENUE TO THE WASTEWATER TREATMENT PLANT ON LEAGUE LANE APPROXIMATELY 3,300 FEET LONG IN CHESTERTON INDIANA. THE PREBID MEETING DETAILS ARE POSTED UNDER THIS UPDATE. AMENDMENT 0002 HAS BEEN POSTED. THE BID OPENING DETAILS: https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_f2497b3a6a6a4b9686e9d8ebcd64c537%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22c0ebcabb-6410-4842-9c20-f0509e3c1887%22%7dDial in by phone +1 503-207-9433,,181046699# United States, Beaverton Phone conference ID: 181 046 699#
From Solicitation posted on Mar 10, 2026Notice history
6-
Presolicitation Posted Oct 29, 2025
-
Solicitation Posted Jan 30, 2026View changes (5)
- Title: W912P626BA003 Chesterton Interceptor Rehabilitation → W912P626BA003 Chesterton Interceptor Rehab
- Description: Description was updated
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Nov 16, 2025 → Mar 04, 2026
- Set-Aside: Total Small Business Set-Aside (FAR 19.5) → None
-
Solicitation Posted Feb 02, 2026No changes from previous notice
-
Solicitation Posted Mar 02, 2026View changes (2)
- Description: Description was updated
- Response Deadline: Mar 04, 2026 → Mar 11, 2026
Details
Award Information
Not yet awarded
Contacts
Phone
Phone
Agency
Place of Performance