USDA-NRCS-TX - Hickory Creek Watershed Site 11 & 14 Repairs in Denton County 12FPC325B0006
Summary
AI-generated · Aug 27, 2025Repair of Sites 11 and 14 in the Hickory Creek Watershed, Denton County, TX, requires a firm-fixed-price construction contract to be awarded by sealed bidding as a Total Small Business Set-Aside. Work includes stripping and stockpiling topsoil, excavating and filling to achieve the rock riprap subgrade, placing and anchoring geotextile fabric, installing rock riprap to the specified thickness and limits, backfilling the toe with earthen materials, blending earthwork into the existing embankment, establishing vegetation, and reconstructing fences above the riprap on both upstream wave berms; the plunge basin will be armored with a 2-foot-thick blanket of rock riprap to retard erosion. Site work is to be completed one site at a time. The estimated magnitude is between $1.25 million and $1.75 million, with a bid guarantee of 20% of the bid price or $3 million, whichever is less. A mandatory site visit is scheduled for 8/13/2025 at 10:00 AM at 525 S. Loop 288 Suite C-1, Denton, TX 76205. See the attached combined synopsis/SOW for full details.
There are multiple postings of this solicitation with identical requirements; no substantive changes appear between notices beyond minor textual differences.
Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 05, 2025Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 *Site work will be completed one at a time, finish one site requried work then will move on to the other site to begin work. The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 08, 2025Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 *Site work will be completed one at a time, finish one site requried work then will move on to the other site to begin work. The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 12, 2025Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 *Site work will be completed one at a time, finish one site requried work then will move on to the other site to begin work. The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 14, 2025Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 *Site work will be completed one at a time, finish one site requried work then will move on to the other site to begin work. The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 22, 2025Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 *Site work will be completed one at a time, finish one site requried work then will move on to the other site to begin work. The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
From Combined Synopsis/Solicitation posted on Aug 26, 2025Notice history
6-
Combined Synopsis/Solicitation Posted Aug 05, 2025
-
Combined Synopsis/Solicitation Posted Aug 08, 2025View changes (1)
- Description: Description was updated
-
Combined Synopsis/Solicitation Posted Aug 12, 2025No changes from previous notice
-
Combined Synopsis/Solicitation Posted Aug 14, 2025No changes from previous notice
-
Combined Synopsis/Solicitation Posted Aug 22, 2025No changes from previous notice
-
Combined Synopsis/Solicitation LATEST Posted Aug 26, 2025View changes (1)
- Response Deadline: Aug 26, 2025 → Aug 27, 2025