TAMPA HARBOR, DREDGE MATERIAL MANAGEMENT AREA 3-D SITE IMPROVEMENTS AND MAINTENANCE, HILLSBOROUGH COUNTY, FLORIDA W912EP26CA009
Summary
AI-generated · Jan 17, 2026Construction of two new weir structures in the DMMA 3-D basin, including concrete foundations, discharge pipes, filter drain and CLSM, helical anchors, mitered end sections, a riprap outfall area, a floating platform, a gangway, and a flap gate. The project also covers deconstructing the existing dike near the new weirs, reconstructing the dike, and creating new earthwork features such as ramps. It includes repair and stabilization of eroded sections of the exterior dike slope with fill, riprap, and sod.
Also required are the removal and replacement of the damaged gangway at the existing weirs, modification of the floating dock at the existing weirs to ensure proper operation (per Appendix A: Shop Drawings of Existing Weirs), and concrete repairs at the existing weirs. Awarded to SpectraServ Inc.
The project consists of the construction of two new weir structures in the DMMA 3-D basin. The weir construction also includes associated concrete foundation, discharge pipes, filter drain and CLSM, helical anchors, mitered end sections, riprap outfall area, floating platform, gangway, and flap gate. Associated earthwork includes deconstruction of the existing dike in the vicinity of the new weirs; reconstruction of the dike; and construction of new earthwork features including ramps. The project also entails repair and stabilization of eroded sections of the existing exterior dike slope, including placement of fill, riprap, and sod. The gangway at the existing weirs is damaged and requires removal and replacement. The floating dock at the existing weirs requires modification to allow for proper operation (See Appendix A: Shop Drawings of Existing Weirs). Concrete repairs are also required at the existing weirs.
From Award Notice posted on Jan 16, 2026Notice history
1Details
Award Information
Award Notices
Posted: Jan 16, 2026
The project consists of the construction of two new weir structures in the DMMA 3-D basin. The weir construction also includes associated concrete foundation, discharge pipes, filter drain and CLSM, helical anchors, mitered end sections, riprap outfall area, floating platform, gangway, and flap gate...
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| SPECTRASERV INC | R7SBDKY7MW98 | 0NUH2 | Kearny, NJ |
Contacts
Phone
Phone
Agency
Place of Performance
USA