Septic Drain Pump and Drain Field Installation for USDA ARS in Pullman, WA 1232SA25Q0645
Summary
AI-generated · Aug 24, 2025Provide all labor, materials, equipment, supplies, supervision, and transportation needed to install a septic drain pump and drain field at a federal facility in Pullman, WA, performing the work in accordance with the Statement of Work and all attached documents. Quotes are requested and must follow the SOW and attachments; review the response instructions in the attachments for submission details.
The project value is estimated between $25,000 and $100,000, with completion required within 180 days after Notice to Proceed. If required, bid bonds are due 10 days after award. The work is governed by the Department of Labor General Decision WA20250042 (dated 08/08/2025). Additional important response information is provided in the attachments.
Thisi a solicitation/request for qutoes to provide all labor, materials, equipment, supplies, supervision, and transportation needed for drain pump and drain field installation for USDA ARS in Pullman, WA. All work shall be done IAW the Statement of Work (SOW) and other attachments set forth in this solicitation. IAW FAR 36.204 the estimated magnitude for this project is between $25,000 and $100,000. Completion shall be 180 days after Notice to Proceed with bonds due 10 days after award if required. Dept. of Labor General Decision #WA20250042 dated 08/08/2025 is applicable to this requirement. Please see the attachments for important information on when and how to respond along with other necssary details in the attachments.
From Solicitation posted on Aug 15, 2025NOTE: This solciiation is amended to correct the statement of work (SOW) to include the electrical work. Please see the attached SF30 and revised statment of work. Acknowledgemen of the amendment is required with quoatation on the SF1442. This is a solicitation/request for qutoes to provide all labor, materials, equipment, supplies, supervision, and transportation needed for drain pump and drain field installation for USDA ARS in Pullman, WA. All work shall be done IAW the Statement of Work (SOW) and other attachments set forth in this solicitation. IAW FAR 36.204 the estimated magnitude for this project is between $25,000 and $100,000. Completion shall be 180 days after Notice to Proceed with bonds due 10 days after award if required. Dept. of Labor General Decision #WA20250042 dated 08/08/2025 is applicable to this requirement. Please see the attachments for important information on when and how to respond along with other necssary details in the attachments.
From Solicitation posted on Aug 26, 2025Notice history
2-
Solicitation Posted Aug 15, 2025
-
Solicitation LATEST Posted Aug 26, 2025View changes (2)
- Title: Septic Drain Pump and Drain Field Installation for USDA ARS in Pullman, WA → (Amended) Septic Drain Pump and Drain Field Installation for USDA ARS in Pullman, WA
- Description: Description was updated
Details
Award Information
Not yet awarded
Contacts
Agency
Place of Performance