Contacts, documents and full notice history are available with a subscription.
Award Notice SBA 4 notices 10 documents

Replace Greenhouse Floor Drain in College Station, TX 1232SA25Q0624

Solicitation 1232SA25Q0624 Copied Notice ID b2e2bedb76014606adbaca13817e42f9 Copied AGRICULTURE, DEPARTMENT OF — USDA ARS AFM APD
SAM.gov
Posted
Aug 13, 2025
Deadline
Sep 04, 2025
Set-aside
SBA
NAICS
238190
PSC
Y1PZ

Summary

AI-generated · Aug 24, 2025

The scope covers repair and replacement of a floor drain for a USDA greenhouse in College Station, TX, and the contractor must be familiar with all aspects of the solicitation documents and the SOW/Specifications. A mandatory site visit is required prior to bidding.

For inquiries, submit written questions to the designated point of contact by 4:00 PM on August 27, 2025; responses will be posted on sam.gov. Late questions may not be answered, and if you submit questions after the deadline and you did not attend the site visit, you may not be technically eligible for award under the specified evaluation factor, and a response may not be provided.

Contractor shall have knowledge of all aspects pertaining to the Solicitation Documents. The SOW and Specifications are written for the repair/replacement of floor drain for a USDA greenhouse in College Station, TX. There IS a mandatory site visit to attend. Please see paragraph L.6. All RFI questions pertaining to this project must be submitted in writing to the POC (david.hildebrand@usda.gov) of this solicitation. Responses to RFI questions will only be posted on sam.gov. To ensure a response, questions must be submitted by 4:00 PM August 27th, 2025. Questions submitted after August 27th until quotes are due may not receive a response. If questions are submitted after August 27th and you were not an attendee of a site visit and therefore would not be technically acceptable for award under Evaluation Factor 4, a response will not be provided.

From Solicitation posted on Aug 13, 2025

Contractor shall have knowledge of all aspects pertaining to the Solicitation Documents. The SOW and Specifications are written for the repair/replacement of floor drain for a USDA greenhouse in College Station, TX. There IS a mandatory site visit to attend. Please see paragraph L.6. All RFI questions pertaining to this project must be submitted in writing to the POC (david.hildebrand@usda.gov) of this solicitation. Responses to RFI questions will only be posted on sam.gov. To ensure a response, questions must be submitted by 4:00 PM August 27th, 2025. Questions submitted after August 27th until quotes are due may not receive a response. If questions are submitted after August 27th and you were not an attendee of a site visit and therefore would not be technically acceptable for award under Evaluation Factor 4, a response will not be provided.

From Solicitation posted on Aug 25, 2025

Contractor shall have knowledge of all aspects pertaining to the Solicitation Documents. The SOW and Specifications are written for the repair/replacement of floor drain for a USDA greenhouse in College Station, TX. There IS a mandatory site visit to attend. Please see paragraph L.6. All RFI questions pertaining to this project must be submitted in writing to the POC (david.hildebrand@usda.gov) of this solicitation. Responses to RFI questions will only be posted on sam.gov. To ensure a response, questions must be submitted by 4:00 PM August 27th, 2025. Questions submitted after August 27th until quotes are due may not receive a response. If questions are submitted after August 27th and you were not an attendee of a site visit and therefore would not be technically acceptable for award under Evaluation Factor 4, a response will not be provided.

From Solicitation posted on Aug 28, 2025

Notice history

4
  1. Solicitation Posted Aug 13, 2025
  2. Solicitation Posted Aug 25, 2025
    No changes from previous notice
  3. Solicitation Posted Aug 28, 2025
    No changes from previous notice
  4. Award Notice LATEST Posted Sep 05, 2025

Details

Solicitation number 1232SA25Q0624
Notice ID b2e2bedb76014606adbaca13817e42f9
Award number 1232SA25C0034
Notice type Solicitation
Product / Service (PSC) Y1PZ
NAICS 238190
Place of performance College Station, Texas
Archive date Sep 19, 2025

Award Information

Awardee
1
Total Awarded
$44,445.00
Award Date
Sep 05, 2025

Awardees

Company Name UEI CAGE Code Location
Shellback Construction LLC Q311XVJAJGT4 8ZTN4 Brenham, TX

Contacts

primary
David Hildebrand

Email

Agency

AGRICULTURE, DEPARTMENT OF
AGRICULTURAL RESEARCH SERVICE
USDA ARS AFM APD

Place of Performance

College Station, Texas 77845
USA

Dates

Posted Aug 13, 2025 11 months ago
Last Updated Aug 06, 2026 2 days ago
Due Sep 04, 2025 11 months ago