Repair Waterfront – Phase 2 at USCG Station Portsmouth Harbor (New Castle, New Hampshire) 70Z0G126BSNNE8241
Summary
AI-generated · Mar 11, 2026Repair Waterfront Phase 2 at USCG Station Portsmouth Harbor requires a firm-fixed-price construction contract for base scope plus two optional bid items. Base work covers: bulkhead repairs and repointing along the North Quay Wall; paving repairs and void/sinkhole work in the east dumpster pad area (including partial demolition, installation of a concrete closure wall, backfill, and paving); removal and replacement of the north quay wall fence; repairs to the South Quay Wall (including an interim stone berm and void repairs); restoration of the north rip-rap revetment; additional paving repairs in the west parking area behind the north revetment; removal and replacement of the top-of-north revetment fence; recoating the Wave Screen guide piles, replacing a broken cleat, and installing sacrificial anodes; and installation of a new timber floating dock to replace the damaged concrete dock. Option Bid Item 1 adds a riprap revetment extension at the west end of the South Quay Wall to address lower-elevation areas; Option Bid Item 2 adds HDPE pile sleeves on existing steel piles. All work must follow the project specifications PSN 16654142, drawings, and applicable codes and permits.
Period of performance is 189 calendar days from Notice to Proceed. If options 1 and 2 are exercised, the completion dates extend by 7 and 14 calendar days, respectively. The project magnitude is between $1,000,000 and $5,000,000. Funds are not presently available; no award will be made until funds are available. Questions during the presolicitation phase will not be answered; submit questions after the solicitation documents are posted. Contractors must be registered in SAM and keep certifications current; the government may cancel the solicitation at any time and is not obligated to reimburse response costs.
Repair Waterfront Phase 2 at USCG Station Portsmouth Harbor (New Castle, New Hampshire) THIS IS A PRESOLICITATION NOTICE ONLY. THIS IS NOT A REQUEST FOR PROPOSAL. NO SPECIFICATIONS OR DRAWINGS ARE AVAILABLE AT THIS TIME. United States Coast Guard Civil Engineering Unit (CEU) Providence announces a requirement for a Firm Fixed Price (FFP) contract for Repair Waterfront Phase 2 at USCG Station Portsmouth Harbor This solicitation will be advertised as a 100% Total Small Business Set Aside. The Northern American Industry Classification System (NAICS) code for this project is 237990. The Invitation for Bid (IFB) will be issued on or about 26 March 2026. The procurement method is Sealed Bidding, FAR Part 14. The offeror is responsible to monitor and download any amendments for the solicitation from the Contract Opportunities (https://sam.gov) website. Project Description: The project consists of (1) base bid and (2) options. Base Bid Item: RPUID 816511, Bulkheads North Quay Wall: Work includes chinking and repointing the quay wall. RPUID 816511, Bulkheads North Quay Wall/RPUID 9383, Paving: Work includes repairing sinkholes/voids in the dumpster pad area at the east of the quay wall, including partial demolition and removal of the concrete slab and debris, excavation and installation of a concrete closure wall, backfill, and placement of base course and bituminous pavement. RPUID 816511, Bulkheads North Quay Wall/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence on the north quay wall, along the limits of repairs. RPUID 816511, Bulkheads - South Quay Wall: Work includes repairing the east wall with interim stone berm, repairing voids in the face of the quay wall, and repairing a sinkhole behind the quay wall. RPUID 857029, Rip-rap: Work includes restoring the north rip-rap revetment. RPUID 857029, Rip-rap/RPUID 9383, Paving: Work includes repairing sinkhole/voids in the west parking area just behind the north revetment, including partial demolition and removal of the existing pavement, backfill, and placement of base course and bituminous pavement. RPUID 857029, Rip-rap/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence at the top of the north revetment, along the limits of repairs. RPUID 50109, Wave Screen: Work includes recoating guide piles from mean-low water to the top of the piles, replacing a broken cleat, and installing sacrificial anodes. RPUID 848538, Floating Dock - Boathouse: Work includes installing a new timber floating dock to replace the previous concrete floating dock that was damaged during a storm and has been removed from the site. Option Bid Item 1: RPUID 816511, Bulkheads - South Quay Wall: Option item includes providing a riprap revetment as an extension to the west end of the existing south quay wall, to fill in lower-elevation areas of the adjacent ledge outcropping. Option Bid Item #2: RPUID 50109, Wave screen/Float dock: Option item includes installing high density polyethylene (HDPE) pile sleeves on the existing steel pile piles. All work shall be accomplished in accordance with the project specifications (PSN 16654142), project drawings, all local, State, and Federal Codes. and all required permitting Period of Performance: The period of performance for the project is 189 calendar days from issuance of Notice to Proceed. *If options 1 & 2 are exercised the Contract Completion Date will be extended as such: - Option Bid Item 1 7 Additional Calendar Days ; - Option Bid Item 2 14 Additional Calendar Days Contract Magnitude: The magnitude of this construction project is between $1,000,000 and $5,000,000 IAW FAR 36.204. General Information: Please be advised of on-line registration requirements in the System for Awards Management (SAM) database www.sam.gov; Representation and Certifications are required to be updated annually as a minimum to keep information current, accurate and complete. The electronic annual representations and certifications are effective until one year from date of submission. Contractors will be searched against SAM to ensure they are eligible for federal contract awards. The information being requested does not constitute a commitment on the part of the Government to award a contract nor to pay for any costs incurred as a result of replying to this notice. QUESTIONS REGARDING THE PROCUREMENT WILL NOT BE ANSWERED DURING THE PRESOLICITATION PHASE. SUBMIT QUESTIONS TO THE CONTRACT SPECIALIST AFTER THE SOLICITATION AND ASSOCIATED DOCUMENTS HAVE BEEN POSTED. NOTE: Funds are not presently available for this effort. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs. (End of Pre-Solicitation Notice)
From Presolicitation posted on Mar 10, 2026USCG CEU PROVIDENCE Solicitation Number: 70Z0G126BSNNE8241 Project Title: Repair Waterfront Phase 2 at USCG Station Portsmouth Harbor, New Castle, New Hampshire Solicitation issued as an Invitation for Bid (IFB) and 100% Total Small Business Set-Aside. All documents for the solicitation are available at https://sam.gov/. Description of Work: The project consists of (1) base bid and (2) options. Base Bid Item: RPUID 816511, Bulkheads North Quay Wall: Work includes chinking and repointing the quay wall. RPUID 816511, Bulkheads North Quay Wall/RPUID 9383, Paving: Work includes repairing sinkholes/voids in the dumpster pad area at the east of the quay wall, including partial demolition and removal of the concrete slab and debris, excavation and installation of a concrete closure wall, backfill, and placement of base course and bituminous pavement. RPUID 816511, Bulkheads North Quay Wall/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence on the north quay wall, along the limits of repairs. RPUID 816511, Bulkheads - South Quay Wall: Work includes repairing the east wall with interim stone berm, repairing voids in the face of the quay wall, and repairing a sinkhole behind the quay wall. RPUID 857029, Rip-rap: Work includes restoring the north rip-rap revetment. RPUID 857029, Rip-rap/RPUID 9383, Paving: Work includes repairing sinkhole/voids in the west parking area just behind the north revetment, including partial demolition and removal of the existing pavement, backfill, and placement of base course and bituminous pavement. RPUID 857029, Rip-rap/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence at the top of the north revetment, along the limits of repairs. RPUID 50109, Wave Screen: Work includes recoating guide piles from mean-low water to the top of the piles, replacing a broken cleat, and installing sacrificial anodes. RPUID 848538, Floating Dock - Boathouse: Work includes installing a new timber floating dock to replace the previous concrete floating dock that was damaged during a storm and has been removed from the site. Option Bid Item 1: RPUID 816511, Bulkheads - South Quay Wall: Option item includes providing a riprap revetment as an extension to the west end of the existing south quay wall, to fill in lower-elevation areas of the adjacent ledge outcropping. Option Bid Item #2: RPUID 50109, Wave screen/Float dock: Option item includes installing high density polyethylene (HDPE) pile sleeves on the existing steel pile piles. All work shall be accomplished in accordance with the project specifications (PSN 16654142), project drawings, all local, State, and Federal Codes. and all required permitting NAICS Code: 237990 -- Other Heavy and Civil Engineering Construction SBA Size Standard: $45.0 Million Construction Magnitude: The magnitude of this construction project is between $1,000,000 and $5,000,000 IAW FAR 36.204. Product Service Code (PSC): Z2PZ IMPORTANT DATES & DEADLINES: Bid Due Date: 29 April 2026 at 2:00PM EST Request for Information (RFI)/Questions Due Date: 14 April 2026 at 2:00PM EST Site Visit Date: 8 April 2026 at 11:00AM EST (see page 94 of solicitation for site visit details) Contract Completion Date (CCD): The CCD for the base bid is 189 calendar days from issuance of Notice to Proceed. *If options 1 & 2 are exercised the Contract Completion Date will be extended as such: - Option Bid Item 1 7 Additional Calendar Days ; - Option Bid Item 2 14 Additional Calendar Days Bid guarantee required. Submit in writing all questions regarding the solicitation to the Point of Contact (POC): Cam Ormiston at Cameron.h.ormiston@uscg.mil Potential bidders must be currently registered in the System for Award Management (SAM) to be eligible for award. (See internet site https://www.sam.gov) NOTE: THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS SOLICITATION NOTICE OR ANY FOLLOW-UP INFORMATION REQUEST. (End of Solicitation Notice)
From Solicitation posted on Mar 26, 2026USCG CEU PROVIDENCE Solicitation Number: 70Z0G126BSNNE8241 ABSTRACT OF BIDS ATTACHED FOR REPAIR WATERFRONT - PHASE 2 Amendment 0001 - 14 April 2026- Amendment 0001 provides a copy of the pre-bid site visit sign-in sheet (Attachment 6), for Solicitation #70Z0G126BSNNE8241 (see full amendment included in attachments section for all information and documents) Project Title: Repair Waterfront Phase 2 at USCG Station Portsmouth Harbor, New Castle, New Hampshire Solicitation issued as an Invitation for Bid (IFB) and 100% Total Small Business Set-Aside. All documents for the solicitation are available at https://sam.gov/. Description of Work: The project consists of (1) base bid and (2) options. Base Bid Item: RPUID 816511, Bulkheads North Quay Wall: Work includes chinking and repointing the quay wall. RPUID 816511, Bulkheads North Quay Wall/RPUID 9383, Paving: Work includes repairing sinkholes/voids in the dumpster pad area at the east of the quay wall, including partial demolition and removal of the concrete slab and debris, excavation and installation of a concrete closure wall, backfill, and placement of base course and bituminous pavement. RPUID 816511, Bulkheads North Quay Wall/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence on the north quay wall, along the limits of repairs. RPUID 816511, Bulkheads - South Quay Wall: Work includes repairing the east wall with interim stone berm, repairing voids in the face of the quay wall, and repairing a sinkhole behind the quay wall. RPUID 857029, Rip-rap: Work includes restoring the north rip-rap revetment. RPUID 857029, Rip-rap/RPUID 9383, Paving: Work includes repairing sinkhole/voids in the west parking area just behind the north revetment, including partial demolition and removal of the existing pavement, backfill, and placement of base course and bituminous pavement. RPUID 857029, Rip-rap/RPUID 810801 Fence/RPUID 858649 Waterfront Fence: Work includes removing and replacing the existing fence at the top of the north revetment, along the limits of repairs. RPUID 50109, Wave Screen: Work includes recoating guide piles from mean-low water to the top of the piles, replacing a broken cleat, and installing sacrificial anodes. RPUID 848538, Floating Dock - Boathouse: Work includes installing a new timber floating dock to replace the previous concrete floating dock that was damaged during a storm and has been removed from the site. Option Bid Item 1: RPUID 816511, Bulkheads - South Quay Wall: Option item includes providing a riprap revetment as an extension to the west end of the existing south quay wall, to fill in lower-elevation areas of the adjacent ledge outcropping. Option Bid Item #2: RPUID 50109, Wave screen/Float dock: Option item includes installing high density polyethylene (HDPE) pile sleeves on the existing steel pile piles. All work shall be accomplished in accordance with the project specifications (PSN 16654142), project drawings, all local, State, and Federal Codes. and all required permitting NAICS Code: 237990 -- Other Heavy and Civil Engineering Construction SBA Size Standard: $45.0 Million Construction Magnitude: The magnitude of this construction project is between $1,000,000 and $5,000,000 IAW FAR 36.204. Product Service Code (PSC): Z2PZ IMPORTANT DATES & DEADLINES: Bid Due Date: 29 April 2026 at 2:00PM EST Request for Information (RFI)/Questions Due Date: 14 April 2026 at 2:00PM EST Site Visit Date: 8 April 2026 at 11:00AM EST (see page 94 of solicitation for site visit details) Contract Completion Date (CCD): The CCD for the base bid is 189 calendar days from issuance of Notice to Proceed. *If options 1 & 2 are exercised the Contract Completion Date will be extended as such: - Option Bid Item 1 7 Additional Calendar Days ; - Option Bid Item 2 14 Additional Calendar Days Bid guarantee required. Submit in writing all questions regarding the solicitation to the Point of Contact (POC): Cam Ormiston at Cameron.h.ormiston@uscg.mil Potential bidders must be currently registered in the System for Award Management (SAM) to be eligible for award. (See internet site https://www.sam.gov) NOTE: THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS SOLICITATION NOTICE OR ANY FOLLOW-UP INFORMATION REQUEST. (End of Solicitation Notice)
From Solicitation posted on Apr 29, 2026Notice history
3-
-
Solicitation Posted Mar 26, 2026View changes (3)
- Description: Description was updated
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Mar 26, 2026 → Apr 29, 2026
Details
Award Information
Not yet awarded