AI-generated · Nov 15, 2025Remove the existing Weil McClain water-tube boiler (209 MBH) from the Building 6 mechanical room and install a CSD-1 compliant boiler sized to match the existing capacity, on the same equipment pad. Use existing utility lines for tie-ins where possible, but install a new PVC vent line (per NBCI code) and replace the atmospheric metal duct as needed. Confirm the feasibility of utility tie-ins and vent-line replacement during a pre-bid walk-through; some minor space-fitting modifications may be required. Follow the boiler manufacturer install instructions and ensure ICRA safety requirements are met; provide disposal receipts for the old boiler.
Provide all materials, labor, equipment, and supervision, with a warranty and start-up to verify proper operation after installation. Dispose of the existing boiler with receipts submitted to VA. The work must comply with all relevant local, state, federal, and VA specifications and be completed within 30 calendar days from Notice to Proceed.
Page 1 of 1 SCOPE OF WORK LR Bldg 6 Boiler Replacement Project: 512-25-052 GENERAL SCOPE OF WORK: The contractor will provide all material, labor, equipment, and supervision necessary to complete the above-named project at the VA Maryland Health Care System (VAMHCS), Loch Raven Campus. Contractor is to remove the existing boiler in the Building 6 mechanical room a Weil McClain Water Tube Boiler rated at 209MBH and replace it with a CSD-1 compliant boiler on the existing equipment pad. The old boiler should be properly disposed of after removal with disposal receipts provided to VA. New boiler should use existing utility lines for tie-in s where possible except for the existing Vent line. Per NBCI code, the vent line must be PVC and the atmospheric metal duct deteriorate. Contractor to confirm feasibility of utility line tie-ins and vent line replacement during pre-bid walk through. Utility tie-ins may require minor modifications to fit the existing space and new boiler. Contractor to follow boiler manufacturer install instructions for proper installation. Contractor will provide materials to meet ICRA requirements set forth by safety based on the work to be completed. Contractor to provide warranty and start-up after install of new boiler to confirm proper operation. Remove and dispose of existing Weil McClain Water Tube Boiler (209MBH). Provide disposal receipts to VA. Provide and install CSD-1 compliant Boiler sized to match existing boiler. Utilize existing utility lines for tie-ins where possible except for the vent line. New PVC vent line must be installed. Contractor to adhere to any and all local, state, federal, and VA specifications and guidelines. Work will be completed in 30 calendar days from Notice To Proceed.
From Combined Synopsis/Solicitation posted on Nov 14, 2025Notice history
1-
Combined Synopsis/Solicitation LATEST Posted Nov 14, 2025
Details
Award Information
Contacts
Contracting Officer
Phone
Agency
Place of Performance
FMS 10 N Greene St
Baltimore, Maryland 21201
USA