MONO REHAB GAMBRILL MILL SIDEWALK 140P3025Q0040
Summary
AI-generated · Aug 25, 2025Rehabilitate the Gambrill Mill sidewalk by removing the existing flagstone sidewalk and setting bed, replacing about 40% of the flagstone that is broken or delaminated, and relaying the entire sidewalk with the existing unbroken stones plus replacement stones in a new mortar bed with flush joints to match the existing appearance. The scope also includes removing the flagpole and replacing wood curbing between the sidewalk and the adjacent asphalt parking lot; provide all labor, supervision, materials, tools, transportation, licenses, permits, PPE, professional services, and equipment necessary to complete the work.
Estimated value range is $25,000 to $100,000, with completion expected 90 calendar days after notice to proceed. For contracts in this range, payment protections must be provided within 10 calendar days after award, options include an irrevocable letter of credit, a payment bond, or a certificate of deposit.
140P3025Q0040 MONO Rehab Gambrill Mill Sidewalk Combined Synopsis/Solicitation - Construction This is a combined synopsis/solicitation for construction prepared in accordance with FAR Part 13, Simplified Acquisition Procedures, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a separate written solicitation will not be issued. This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2025-05 Dated: August 7, 2025. This acquisition will be a competitive 100% Small Business Set-Aside. The Associated NAICS code is 238140 with a small business size of $19.0 Million. The magnitude for this requirement IAW FAR 36.204(b) is between $25,000 and $100,000. See Section J for the List of Attachments. IAW FAR 28.102-1(b) and FAR 52.228-13, payment protections are required for construction contracts greater than $35,000 but not greater than $150,000, the successful offeror shall furnish one of the following payment protections within 10 calendar days after award: 1. Irrevocable letter of credit; 2. Payment Bond; or 3. Certificate of deposit The anticipated contract completion date is 90 calendar days after Notice to Proceed (NTP). The contractor must provide all labor, supervision, materials, tools, supplies, transportation, license, certificates, permits, personal protection equipment, professional services, and equipment incidental to and necessary to provide removal of existing flagstone sidewalk and setting bed, replacement of approximately 40% of existing flagstone that are broken or delaminated, relaying the sidewalk in its entirety with the existing unbroke and replacement stone in a new mortar bed with flush joints to match existing, removing flagpole, and replacing wood curbing between sidewalk and asphalt parking lot.
From Combined Synopsis/Solicitation posted on Aug 23, 2025MONO FY25 REHAB GAMBRILL MILL SIDEWALK
From Award Notice posted on Sep 19, 2025Notice history
2-
Combined Synopsis/Solicitation Posted Aug 23, 2025
-
Award Notice LATEST Posted Sep 19, 2025
Details
Award Information
Award Notices
Posted: Sep 19, 2025
MONO FY25 REHAB GAMBRILL MILL SIDEWALK
Awardees
| Company Name | UEI | CAGE Code | Location |
|---|---|---|---|
| GALICIA CONSTRUCTION CORP | Y3DPKJN95HX7 | 5VF58 | Fairfax Station, VA |
Contacts
Phone