Maintenance Dredging of NY & NJ Channels, Arthur Kill 35’ Reach, Federal Navigation Project W912DS26BA013
Summary
AI-generated · Feb 28, 2026Dredging is required to maintain the Arthur Kill 35 Reach portion of the New York–New Jersey Channels, removing about 150,000 cubic yards of shoals to a depth of -35 feet MLLW with up to 1 foot overdepth. The material, mainly silt with some sand and clay, must be processed and transported to a contractor-furnished, state-permitted upland placement site. Because of state water quality restrictions, a mechanical dredge using an environmental clamshell bucket is required, and multiple barges and tugboats will be used for dredging, dewatering, and unloading. The material must meet all federal, state, and local placement criteria, and the contractor will provide all necessary placement permits.
Bidder responsibilities include providing copies of all required permits and approvals for transportation, dewatering, processing, and final placement within 35 days of being deemed apparent low bidder. After award, work must begin within 5 days and maintain an integrated production rate of at least 2,500 cubic yards per calendar day throughout dredging, transportation, processing, dewatering, and placement. The project may impact ship traffic, so the rate must be sustained while minimizing downtime. Plans and specifications are expected April 2026, with bid opening in May 2026, and award anticipated June/July 2026; work is planned between October and December 2026. Estimated project value ranges from $10 million to $25 million, with liquidated damages of $3,230 per calendar day of delay. This is unrestricted procurement.
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.
From Presolicitation posted on Feb 27, 2026The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.
From Solicitation posted on Apr 29, 2026The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.
From Solicitation posted on Jun 04, 2026Notice history
3-
Presolicitation Posted Feb 27, 2026
-
Solicitation Posted Apr 29, 2026View changes (4)
- Title: Maintenance Dredging of NY & NJ Channels, Arthur Kill 35’ Reach, Federal Navigation Project → Maintenance Dredging of New York and New Jersey Channels – Arthur Kill 35’ Reach, Federal Navigation Project
- Notice Type: Presolicitation → Solicitation
- Response Deadline: Mar 31, 2026 → May 27, 2026
- Set-Aside: No Set aside used → None
-
Solicitation LATEST Posted Jun 04, 2026View changes (1)
- Response Deadline: May 27, 2026 → Jun 04, 2026
Details
Award Information
Not yet awarded
Contacts
Phone
Agency
Place of Performance