Contacts, documents and full notice history are available with a subscription.
Solicitation NONE Expired 3 notices

Maintenance Dredging of NY & NJ Channels, Arthur Kill 35’ Reach, Federal Navigation Project W912DS26BA013

Solicitation W912DS26BA013 Copied Notice ID 8c61fc92249f471a9ecae786bd6e7c5c Copied DEPT OF DEFENSE — W2SD ENDIST NEW YORK
SAM.gov
Posted
Feb 27, 2026
Deadline
Mar 31, 2026
Set-aside
NONE
NAICS
237990
PSC
Y1KF

Summary

AI-generated · Feb 28, 2026

Dredging is required to maintain the Arthur Kill 35 Reach portion of the New York–New Jersey Channels, removing about 150,000 cubic yards of shoals to a depth of -35 feet MLLW with up to 1 foot overdepth. The material, mainly silt with some sand and clay, must be processed and transported to a contractor-furnished, state-permitted upland placement site. Because of state water quality restrictions, a mechanical dredge using an environmental clamshell bucket is required, and multiple barges and tugboats will be used for dredging, dewatering, and unloading. The material must meet all federal, state, and local placement criteria, and the contractor will provide all necessary placement permits.

Bidder responsibilities include providing copies of all required permits and approvals for transportation, dewatering, processing, and final placement within 35 days of being deemed apparent low bidder. After award, work must begin within 5 days and maintain an integrated production rate of at least 2,500 cubic yards per calendar day throughout dredging, transportation, processing, dewatering, and placement. The project may impact ship traffic, so the rate must be sustained while minimizing downtime. Plans and specifications are expected April 2026, with bid opening in May 2026, and award anticipated June/July 2026; work is planned between October and December 2026. Estimated project value ranges from $10 million to $25 million, with liquidated damages of $3,230 per calendar day of delay. This is unrestricted procurement.

The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.

From Presolicitation posted on Feb 27, 2026

The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.

From Solicitation posted on Apr 29, 2026

The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35 Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35 Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.

From Solicitation posted on Jun 04, 2026

Notice history

3
  1. Presolicitation Posted Feb 27, 2026
  2. Solicitation Posted Apr 29, 2026
    • Title: Maintenance Dredging of NY & NJ Channels, Arthur Kill 35’ Reach, Federal Navigation ProjectMaintenance Dredging of New York and New Jersey Channels – Arthur Kill 35’ Reach, Federal Navigation Project
    • Notice Type: PresolicitationSolicitation
    • Response Deadline: Mar 31, 2026May 27, 2026
    • Set-Aside: No Set aside usedNone
  3. Solicitation LATEST Posted Jun 04, 2026
    • Response Deadline: May 27, 2026Jun 04, 2026

Details

Solicitation number W912DS26BA013
Notice ID 8c61fc92249f471a9ecae786bd6e7c5c
Notice type Presolicitation
Product / Service (PSC) Y1KF
NAICS 237990
Set-aside No Set aside used
Place of performance USA
Archive date Apr 15, 2026

Award Information

Not yet awarded

Documents

No files available

View on SAM.gov

Contacts

primary
Orlando Nieves

Email

secondary
Matthew Lubiak

Email

Phone

Agency

DEPT OF DEFENSE
DEPT OF THE ARMY
US ARMY CORPS OF ENGINEERS
ENGINEER DIVISION NORTH ATLANTIC
ENDIST NEW YORK
W2SD ENDIST NEW YORK

Place of Performance


USA

Dates

Posted Feb 27, 2026 5 months ago
Last Updated Aug 06, 2026 2 days ago
Due Mar 31, 2026 4 months ago