Kinzua Dam Electric Service Replacement W911WN26QA005

Solicitation W911WN26QA005 Copied Notice ID 39e2bf057ba249b193b097d91f8fb1c8 Copied DEPT OF DEFENSE — W072 ENDIST PITTSBURGH
SAM.gov
Posted
Oct 02, 2025
Deadline
Oct 23, 2025
Set-aside
SBA
NAICS
238210
PSC
Z2NZ

Summary

AI-generated · Oct 09, 2025

Replace the existing partly underground electrical service at Kinzua Dam. The service runs from the meter on a wood panel beside the meter pole, underground to a disconnect switch on the dam exterior, then through exterior rigid metal conduit to an interior automatic transfer switch (ATS). The underground conductors have failed and a temporary aerial feed is in place; the remaining cables from the disconnect to the ATS have very low insulation resistance. Remove and dispose of all conductors from the meter to the ATS and install a new power cable in the existing conduits. Replace the underground conduit in its entirety and replace the end-of-dam disconnect box with a new pull box.

The contractor must remove the temporary power feed after completion, arrange all required inspections, and coordinate with the electric utility (Penelec) to reconnect commercial power. The work includes bituminous pavement removal, trenching and installation of underground conduit, trench backfilling, and other incidental tasks.

The existing electrical service is a partly underground system beginning at the electric meter on wood panel next to the meter pole that then travels underground to a disconnect switch located on the exterior of the dam (see contract drawings), then travels through rigid metal conduit on the exterior of the dam and ends at the automatic transfer switch in the interior of the dam. The existing underground power service conductors have failed and have been bypassed with a temporary aerial service, while the remaining cables from the disconnect switch on the dam to the ATS have very low insulation resistance values. All the power conductors from the meter to the ATS shall be removed and disposed of and new power cable installed in the existing conduits. The underground conduit shall be replaced in its entirety, and the disconnect box at the end of dam shall be replaced with a new pull box. The contractor shall be required to remove the temporary power feed at the completion of the work, arrange for all required inspections, and arrange for the electric utility company, Penelec, to reconnect commercial power. The work also includes bituminous pavement removal, trenching and installation of underground conduit, trench backfilling and other incidental work.

From Solicitation posted on Oct 02, 2025

Notice history

1
  1. Solicitation LATEST Posted Oct 02, 2025 View

Details

Solicitation number W911WN26QA005
Notice ID 39e2bf057ba249b193b097d91f8fb1c8
Notice type Solicitation
Product / Service (PSC) Z2NZ
NAICS 238210
Archive date Dec 29, 2025

Award Information

Not yet awarded

Documents

No files available

View on SAM.gov

Contacts

primary
RAELYN DAY

Email

Phone

Agency

DEPT OF DEFENSE
DEPT OF THE ARMY
US ARMY CORPS OF ENGINEERS
ENGINEER DIVISION GREAT LAKES AND OHIO
W072 ENDIST PITTSBURGH

Place of Performance

1205 Kinzua Rd Warren, PA 16365-5501
16365

Dates

Posted Oct 02, 2025 10 months ago
Last Updated Aug 06, 2026 1 day ago