Jetty Rehabilitation of Cheesequake Creek, NJ Federal Navigation Project W912DS25BA010
Summary
AI-generated · Jul 09, 2026Rehabilitate the eastern jetty of Cheesequake Creek to modern standards, raising its height to match the western jetty. About 17,832 cubic yards of material will be excavated to a depth of -9 MLLW, using heavy civil equipment. The eastern jetty will be rebuilt to the same elevation as the western jetty, and excavated material must meet all applicable federal, state, and local disposal criteria; disposal near a Superfund site may require additional measures and approvals.
Jetty height will be 8 feet with an 11-foot crest width and 1.5 to 1 side slopes. The work is expected to take 6–9 months. Environmental window constraints may require work within specified windows, with environmental monitoring or pauses as needed. Start within five calendar days of notice to proceed and complete the basic work ready for use within 270 calendar days after NTP. The project is estimated at $10–$15 million and is unrestricted; plans and specifications will be issued to bidders, with the procurement proceeding through bid opening, award, and issuance of the NTP in due course.
Advance Notice to Bidders for the Jetty Rehabilitation of Cheesequake Creek, New Jersey, NJ Federal Navigation Project The U.S. Army Corps of Engineers, New York District intends to issue an Invitation for Bid (IFB) for the Jetty Rehabilitation of Cheesequake Creek, New Jersey, NJ Federal Navigation Project. The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform the rehabilitation of the eastern jetty of Cheesequake Creek, New Jersey. The proposed rehabilitation would involve restoring the jetty to modern standards, which includes raising the height to match the western jetty. Through Jetty construction activities, approximately 17,832 cubic yards of material will be dug up to a depth of -9 mean lower low water (MLLW). Rehabilitation & Construction efforts of the eastern Jetty will be accomplished by a variety of heavy civil equipment. Only the eastern Jetty will be reconstructed to match the elevation of the western jetty. The project may involve excavation & disposal of material near a superfund site, & such additional measures may be drawn for proper transportation and disposal. The excavated material would be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction, where the material and placement sites are located. The height of the jetty will be constructed to 8 feet with an 11 feet crest width and 1.5 to 1 side slopes. Overall duration work time is expected to last 6-9 months. Due to restrictions in the environmental window, the contractor may have to implement additional measures such as working within the environmental window duration while employing environmental monitoring or pausing work within the environmental window and resuming once environmental window reopens. The Contractor will be required to commence work within five (5) calendar days after the date of receipt by him of the notice to proceed, and to prosecute said work diligently and to complete the basic work ready for use not later than two hundred seventy (270) calendar days after the receipt by him of the notice to proceed (NTP). The magnitude of the project is estimated to cost between $10,000,000.00 & $15,000,000.00. Plans & specifications for the subject project would be available June 2025 with bid opening in July 2025. It is the intention of the government to award in August 2025 and issue the NTP in October 2025. This is an unrestricted procurement.
From Special Notice posted on Jul 08, 2026Notice history
1-
Special Notice LATEST Posted Jul 08, 2026
Details
Award Information
Not yet awarded